Module 8
Module 8

Make selections and coordinate procurement

An allowance is a number standing in for a decision you have not made yet. Every one of them has to become a specific product, chosen by a date, verified against the real room, approved in writing, ordered, delivered undamaged and stored somewhere dry, all before the trade who installs it arrives. This module teaches the backward arithmetic that sets those dates, what has to be measured in the field before anything is ordered, what happens at the delivery door, and how one late choice turns into idle days for everyone else.

1. A selection is a decision with three dates Understand

Two words first. A selection is the specific product that will be installed where the drawings or the proposal say something general: not "tile" but a named tile, in a size, a color and a quantity; not "faucet" but a make, model, finish and the number of holes it needs. Procurement is everything between that decision and the item sitting on site, undamaged, ready for the trade who installs it: approval, ordering, lead time, delivery, receiving and storage.

Module 6 built a budget with allowances, and Module 7 showed you how allowances hide inside proposals. This module closes the loop. Every allowance becomes a real number here, and every real number arrives with a date attached. Builders who write about schedule slippage put late owner decisions near the top of the list of causes, and the reason is mechanical rather than moral: the plumber sets the rough-in to the fixture you chose, the fabricator cannot cut stone you have not picked, and a trade who arrives to find no material leaves, and may not have another opening for two weeks.

Every selection carries three dates, and you should be able to say all three for every line in your log:

  • Needed on site. The day the installing trade starts the work that uses it. This comes from the sequence (Module 5) and the look-ahead (Module 9).
  • Order by. Needed-on-site minus the lead time the supplier quoted you in writing, minus a few days for delivery and receiving.
  • Decide by. Order-by minus the time it takes to get the choice approved, field-verified and, where there is one, a shop drawing or template reviewed.

Decide-by is the date that matters to you, because it is the only one you control entirely. The other two belong to the supplier and the trade.

The judgment behind it

Most people set selection deadlines from their own calendar: "we will pick tile after the holidays." The trade's calendar is the one that counts. A deadline built backward from the install date is a fact about the project; a deadline set from when you feel ready is a wish. The log you build in this module replaces wishes with facts, and when a fact is uncomfortable (the tile has to be chosen before demolition starts) it is better to know that in week one than in week five.

Boundary

A selection schedule organizes your decisions. It does not change what the permit requires, what the inspector needs to see, or what your contract says happens when a date is missed. Where a product affects something the drawings or the permit depend on (window sizes, structural hardware, equipment capacity, anything the energy or plumbing review looked at), the designer, engineer or building department decides whether your choice is acceptable, not the course and not the supplier.

2. Decision deadlines, built backward

The arithmetic is simple and you do it once per line:

Decide by = install date − lead time − approval and template time − delivery and receiving buffer.

Install date comes from your sequence. Lead time comes from a written quote; the ranges below are what other people were seeing in 2025 and 2026 according to supplier and trade-press pages, and they are here so you know which items to ask about first, not so you can skip asking. Approval and template time is how long it takes for the person who must approve the choice to look at it, for anything that must be measured in the field to be measured, and for a shop drawing or template to be produced and checked. The buffer is a few working days so that a delivery that arrives Friday afternoon damaged does not become Monday's idle crew.

ItemLead time others reported (ask for a written quote)What has to happen before orderingDecide-by this would imply (illustration from the range at left; compute yours from your quote)
Cabinets, stockAbout two weeks (dealer page)Layout final; appliance dimensions confirmed from the actual units; field measure after demolition if walls move4 to 5 weeks before set date
Cabinets, semi-custom5 to 12 weeks (two dealer guides disagree)Same, plus a shop drawing or dealer layout approved in writing8 to 14 weeks before set date
Cabinets, full custom6 to 20 weeks (remodeler and trade-press figures; one 2025 article describes a shop whose proposal alone took weeks)Shop drawings reviewed and signed; every appliance on the schedule confirmedOften before the permit is issued (see section 5)
Countertops (stone, quartz)Fabrication 1 to 3 weeks after template, plus whatever it takes the yard to get the slab you choseCabinets set, level and anchored; sink, cooktop and faucet on site at template; material chosen and heldMaterial chosen before cabinets are set; template date fixed by the cabinet date
Windows and exterior doors, stock2 to 6 weeks; sometimes in local inventoryRough openings verified against the manufacturer's tables; sizes, handing and glazing match the window schedule6 to 8 weeks before the dry-in date
Windows, custom or special8 to 16 weeks reported on 2026 supplier pages (one of which contrasts it with 20 to 26 weeks in 2022)Same, and confirm with the designer whether plan review could change sizes (egress, energy)Often before the permit; a deliberate risk, section 5
TileStock: days. Imported or special order: weeks; one 2021 report had some lines at 8 weeksLayout drawing or dry-lay to confirm cuts, niches and overage quantity3 to 6 weeks before the setter starts
FlooringStock: days to two weeks. Special order: askThe before-or-after-cabinets decision made (it changes cabinet height and toe-kick); acclimation time on site for wood4 to 6 weeks before install, plus acclimation
Plumbing fixturesIn-stock finishes: days. Made-to-order finishes and sizes: "weeks or months" (supplier page)Rough-in dimensions pulled from the fixture's own installation sheet and given to the plumber before rough-inBefore plumbing rough-in, not before finish plumbing
AppliancesMainstream models: often short. Premium and built-in lines: still a top backorder category in 2026; historically 4 to 6 monthsDimensions, door swings, venting and electrical requirements from the actual unit's installation guide, before the cabinet orderBefore cabinets are ordered; the model drives the cabinet opening
Roof trussesFabricators commonly want a minimum of about four weeksEngineered layout and truss drawings, which the building department often wants to see at framing inspectionAround the foundation stage
Lighting, hardware, paintUsually short; specialty fixtures can be longLighting locations before electrical rough-in; paint before the painter, with sample areas approvedLighting: before rough-in. Hardware and paint: 2 to 3 weeks before the trade

Lead-time figures are from supplier and trade-press pages gathered in 2025 and 2026 for the research behind this course; there is no authoritative national dataset. Treat them as prompts for questions, and build your dates from written quotes. The decide-by column is the course's arithmetic on those ranges, not a figure anyone reported; it shows the method, and your own column will differ.

Decision deadline built backward for a countertop A timeline read from right to left. The install date on the right is fixed by the sequence. To its left, fabrication takes two weeks, before that the template visit, before that the cabinets must be set, and before all of it the material must be chosen and held at the yard. The decide-by date lands about five weeks before install. Install: Mon, week 7 fixed by the sequence Fabrication: 10 days from the fabricator's quote Template: Thu, wk 5 sink, cooktop, faucet on site Cabinets set Mon to Wed, wk 5 Decide by end of week 3 read backward: install − fabrication − template − cabinets set − slab sourcing and hold slab must be in the yard before template day backsplash, finish plumbing, appliances all wait for this
A decide-by date for a countertop, built backward. The install date is the sequence's; the fabrication time is the fabricator's; the template depends on the cabinets; the slab must be chosen and held before template day. The owner's date falls out of other people's dates.

Treat the selection log like the inspection list

Module 5 taught you that inspections are hold points: work stops until the inspector has seen it. Selections are hold points in the same way, and the log should be read in the same spirit. If the deadline for the tile is in week 3 and you are in week 3, that is today's work, whatever else is happening. Contracts handle a missed date in different ways: some extend the schedule, some let the contractor install the standard item the allowance was based on, some stop work and charge to restart. Read yours for the clause; if it is silent, ask before the first deadline, not after the first miss.

3. What must be measured before you order

Drawings are a plan, not a measurement. The second most common procurement failure, after lateness, is an item ordered to a plan dimension that the real building does not have. The table lists what experienced builders verify in the field, and when.

ItemVerify whatWhen, and against what
AppliancesWidth, depth, height, door swing, venting route, electrical and gas requirements, from the actual unit's installation guide (and the unit itself where you can). At least one supplier's guide reports that ranges and refrigerators regularly differ from the published spec sheet.Before the cabinet order, because the cabinet opening is built to the appliance, not the other way round.
CabinetsFinal field measure of every wall, corner, window and ceiling height; where walls are coming out or moving, measure again after demolition. The layout has to be final before plumbing and electrical rough-in, because those are set to the cabinet plan.Final measure after demolition and framing; order only after that measure is on the shop drawing.
CountertopsTemplated by the fabricator, only after cabinets are installed, level and anchored. The sink, cooktop and faucet must be physically on site so cutouts and hole positions are taken from the real objects. Fabricators commonly state that changes after template are not accepted and that cabinets which shift later can crack stone.Template day; nothing is cut before it.
Windows and doorsRough openings on plans are worth double-checking: floor thickness, flashing details and applied sills all change them. Sizes are written width first, then height. Use the manufacturer's rough-opening table for the exact unit; measure each opening in three places and use the smallest; check that the diagonals agree within roughly a quarter inch.After framing for a renovation or addition where openings are framed first; before ordering for a new build where the framer builds to the window order. Confirm which with your framer.
TileA layout drawing or a dry-lay to confirm where cuts fall, where the niche lands, and the pattern; then the overage quantity (often 10 to 15 percent, more for diagonal or large-format layouts, but ask the setter).Before ordering, with the setter's input; before the setter's start date with the material on site.
Fixture rough-in locationsEach plumbing fixture's installation sheet gives the drain and supply positions it needs (a wall-hung toilet or a freestanding tub are the usual surprises). Give the sheets to the plumber before rough-in.Before plumbing rough-in; once the inspection that follows has passed, moving it means reopening work.
Stairs, railings, custom doors, built-insField-measured after framing (stairs) or after drywall (built-ins, custom interior doors), because wall thickness and floor finish change the numbers.After the surface the item meets is actually there.

If you have a general contractor, most of this measuring is usually theirs or the supplier's to do; whose it is on your project is a contract question, so ask. Your job is to know that it has to happen, to ask "has this been field-verified?" before you approve an order, and to make sure the owner-supplied items you are buying get measured by the same rule.

4. Approval before ordering: submittals, shop drawings, release

Who approves, in writing

Every selection needs a person who says "yes, order this," and that yes needs to be on paper or in an email that can be found later. On a project with a general contractor, that is usually a selection sheet or a change order the owner signs and the contractor countersigns. With a designer, the designer confirms the choice matches the design and the schedules and the owner approves the cost. As an owner-builder, you are both, and the discipline is to write the approval down anyway: the item, the quantity, the price, the lead time, the date, and the field verification that was done. A choice made by text message at 9 pm is a choice nobody can find in week six.

Submittals and shop drawings, in plain words

A shop drawing is the fabricator's own drawing of how they will build the thing: the cabinet shop's elevation of your run of cabinets with every width written on it; the truss company's layout; the stair builder's rise and run. A submittal is the package sent for review before fabrication: shop drawings, product data sheets, samples, certificates. The reviewer returns it marked in one of three ways. Approved means build it. Approved as noted means build it with the corrections written on it, which can change a dimension or a material while reading as a yes; read the notes. Revise and resubmit means not yet.

On a small residential job the reviewer is often the builder or the designer rather than an architect, and for off-the-shelf products (windows, for instance) the "shop drawing" is really the window schedule checked against the manufacturer's data. Truss packages are the exception worth knowing: they come with engineered layout and truss design drawings, and the building department often wants to see those at the framing inspection. Keep them.

"Release for fabrication"

Fabricators often use the phrase release for fabrication (or "release to production") for the written go-ahead, after the reviewed shop drawing and after field verification, that lets the shop start cutting material. It is their practice, not an official term, and the words vary; the thing to understand is that it is the point of no return. Before release, a cabinet order can be changed for the cost of a phone call; after it, a changed width is often a new cabinet at your cost. Ask every fabricator what their release step is, who sends it, and what happens to changes after it.

A line you will see

"Approved as noted: verify all dimensions in field." That note on a shop drawing is the fabricator saying they will build to the numbers you confirm, which in practice puts the measuring back on whoever ordered. If that is you, the field verification in section 3 has to be done before you release, and the numbers written on the drawing have to be yours. What the note means under the fabricator's terms if something is wrong is a question for the fabricator, and for an adviser if the stakes are high.

5. Long-lead items and ordering before the permit

Some items take longer to arrive than the permit takes to be issued, and the sequence needs them early: windows for the dry-in, trusses for the roof, custom cabinets for a kitchen that cannot sit open for twelve weeks. Ordering them before the permit is common and sometimes necessary. It is also the clearest example in this course of converting a reversible decision into a commitment.

The risk is specific. Plan review can change things: a window may need to be larger for emergency escape, or a different glazing to meet the energy requirements; a truss profile may change with a structural comment; a wall may not be allowed to move. If you have already released the order, you are likely to own a product you cannot use, and the deposit, restocking fee or full price with it; suppliers generally treat custom and special orders as non-returnable.

A sensible middle path, which experienced builders describe in various forms:

  1. Get everything ready short of release. Quotes, shop drawings, field verification where possible, approvals. The order can then be released the day the permit is issued and loses nothing but the review time.
  2. Ask the designer which items plan review could affect. They know what the reviewer looks at. Items the designer expects the review not to touch (often interior cabinets in a kitchen whose walls are not changing, flooring, most fixtures) carry less risk than items it commonly does (windows, structure, equipment). The designer's list for your project, not this one, is the one to use; the examples here are the usual pattern, not a prediction.
  3. Release early only what is unlikely to change, and write down why. If you are taking the risk, take it knowingly, with the designer's view in writing and the restocking terms in front of you.
  4. Tell the lender, if there is one. Some construction lenders will not pay for materials until they are installed, and some pay for stored materials and deposits differently. An early order you expected a draw to cover may be your cash for months.
Boundary

Whether plan review will change an item is the reviewer's decision, not the designer's prediction and not the supplier's reassurance. Ordering before the permit is a risk you choose; nothing in this module reduces it to zero.

6. Deliveries, storage, returns and owner-supplied items

At the delivery door

A delivery is the moment when damage is most clearly somebody else's problem. Once the paperwork is signed clean, it is much harder to make it anyone else's. Freight and retail pages agree on the routine:

  1. Count against the order before the driver leaves: number of cartons, number of units, the right model numbers on the labels.
  2. Inspect before you sign. Open what can be opened. Look at corners, glass, finished faces. Signing the delivery receipt or bill of lading without noting damage generally accepts the shipment as it is and can waive the claim.
  3. Write damage on the receipt in specific words. "Carton 3 crushed, cabinet door dented" rather than "subject to inspection," which may be treated as a clean signature. If you cannot inspect everything, write what you could not inspect.
  4. Photograph damage with the packaging, before anything is moved, and keep the packaging until the claim is settled.
  5. Refuse the damaged units and accept the rest, if the carrier allows a partial refusal. Refusing everything delays the undamaged parts.
  6. Know the claims window. Two retailers' policies found in the research gave 24 to 48 hours for visible damage and about two weeks for concealed damage or shortages; other suppliers differ, and a freight carrier's window can be different again. Yours is in the supplier's and the carrier's terms; find both before delivery day.
  7. Keep a receiving log: date, carrier, what came, count, condition, who signed, photos. The selection log has a column for it.

If you cannot be there, whoever is must know the routine. A contractor's crew signing for an owner-supplied delivery without inspecting it leaves nobody responsible, which is the subject of the owner-supplied table below.

Storage

The usual advice is dry, flat, off the floor, out of the path of work. Cabinets and millwork want to acclimate in conditioned space; windows are stored upright and protected from impact; flooring acclimates on site for the period the manufacturer states; stone and tile stay in their crates until the setter wants them. The honest version for a small house or a tight lot is that you will not have ideal storage, and the fix is timing rather than space: schedule deliveries as close to the install date as the lead time and the buffer allow, and say so in the order. Where you have no storage at all, ask whether the supplier will hold the order (many will, for a period, sometimes for a fee) and whether the installing trade can receive it directly.

Returns and restocking

Stock items can usually be returned within a window, often with a restocking fee; examples in the research ranged from 10 to 30 percent for appliances and 20 percent for one cabinet line. Custom and special-order items are generally not returnable at all, and installed appliances are commonly not returnable unless defective. Two consequences: order the overage you need, not the overage that feels safe, and do not open or install anything you are not sure of. The second is why the field verification in section 3 happens before the order, not after the delivery.

Owner-supplied items and the gap they create

Buying things yourself is reasonable. Appliances, plumbing fixtures, lighting and sometimes cabinets are commonly owner-supplied, and Module 7's bid package told the bidders so. What the proposal rarely says is what happens when an owner-supplied item is wrong, late or damaged. That is the gap, and you close it in writing before the first order.

When an owner-supplied item is…What usually happens if nothing was agreedWhat to agree in writing
LateThe trade arrives, cannot install, leaves. The contractor treats it as an owner-caused delay: schedule extension, sometimes a return-trip or remobilization charge, idle days for every trade behind it.The needed-on-site date for each item, who tracks it, what notice you will give if it slips, and what a return trip costs.
Wrong (size, finish, handing, rough-in)Reorder at your cost, with the lead time again; the trade may charge to adapt (a new cabinet opening, a moved supply line).Who verifies the item against the schedule and the field before it is ordered; whether the contractor will review your order before you place it.
DamagedIf the contractor's crew signed for it, the carrier claim may be lost and nobody is clearly responsible. If it was fine on delivery and damaged on site later, it is a dispute.Who receives deliveries and inspects them; where items are stored and who is responsible for them once on site; that photos are taken at receipt.
Defective after installationThe contractor's workmanship warranty, as most contracts write it, covers the installation and not the product. Removing and reinstalling a replacement is usually billable.That the product warranty is yours to pursue; what the contractor charges to remove and reinstall.
Missing a part (a trim kit, a mounting bracket, a cartridge)A half-day lost while someone drives to the supply house; the part may be special order.That you will open and check every owner-supplied item against its parts list before the needed-on-site date.

Two more things owner-supplied items change. The contractor's markup on materials usually pays for ordering, receiving and warranty handling; when you buy, you have taken that work on, and the contractor has less reason to chase your delivery. And the lender, if there is one, may treat your purchases outside the contract differently in the draw schedule.

Allowances become real numbers

When a selection is made, the allowance in the contract is replaced by the actual cost, and the difference moves one way or the other. Contracts commonly handle an overage as the difference plus the contractor's markup, and an underage as a credit, sometimes without the markup; yours may do either, and the only way to know is to read it. Three questions settle most arguments before they start: does the allowance include tax and delivery; is the allowance stated at the contractor's cost or at retail; and does the markup apply to the overage. Record each selection's actual cost against its allowance in the budget tracker as it happens, so the reconciliation at the end of the job is a sum and not an investigation.

7. Reading the drawings for selections: the schedules

Module 3 introduced the plan set. The pages that matter for procurement are the schedules: tables in the drawings that list, by a mark, every door, window, fixture or finish, with the properties each one must have. A selection is correct when it matches its schedule line, and incorrect, however nice it is, when it does not, unless the schedule line has been changed in writing by whoever holds the design.

  • Finish schedule. Room by room: floor, base, walls, ceiling, with a material and often a product or an allowance. It is the document that tells you how many tile selections you actually have (the kitchen floor and the backsplash are two lines, not one).
  • Door and window schedule. Each opening has a mark (W1, D3) that appears on the plan. The schedule gives the nominal size, the rough opening or the manufacturer's unit size, the type (casement, double-hung, slider), the glazing, the handing (which side the hinges are on, seen from a stated side), and sometimes the energy values the plan review relied on. Order to the schedule; verify the opening in the field; if the two disagree, that is an RFI (Module 9), not a judgment call.
  • Fixture schedule (plumbing, and often a separate lighting or electrical schedule). Each fixture has a mark (P-1, L-4), a description, sometimes a specified product, and the rough-in requirements the plumber or electrician needs.

Here is a fragment of a fixture schedule, with the lines that catch owner-supplied selections marked.

PLUMBING FIXTURE SCHEDULE (excerpt) P-1 Kitchen sink, undermount, single bowl, stainless, 30 in. min. cabinet, 1 faucet hole, by ownerThe sink the owner is pricing needs a 33-inch base cabinet. The cabinet order says 30. One of them has to change before cabinets are released. P-2 Kitchen faucet, single-hole, pull-down, finish to match P-1 hardware, by owner"To match" is a decision, not a specification. Which finish? The hardware has not been chosen either. P-3 Dishwasher connection, supply and drain per manufacturer, appliance by ownerThe plumber needs the dishwasher's installation sheet before rough-in to place the supply and the air gap, if one is required locally. P-4 Ice maker box, location per appliance, refrigerator by ownerWhich side of the refrigerator bay? From the actual unit's guide, not the catalog. WINDOW SCHEDULE (excerpt) W1 Casement, 2'-6" x 4'-0", R.O. per mfr, hinge left, tempered where within 24" of doorThree things to verify: the opening the framer built, the manufacturer's rough-opening table for this exact unit, and the handing convention the schedule uses (viewed from outside or inside). Ask, and write the answer on the schedule.

The habit to build: before any selection is approved, open the schedule, find the mark, and read the whole line. Then write the mark on the selection log row, so that when the item arrives, whoever receives it can check the label against the line.

8. See it: the Alder Street selection log, and one late choice See it

Fictional example

The Alder Street kitchen continues from Module 7. The owners, M. and J. Osei, signed with Hale & Daughters Construction (Proposal B; Ruth Hale runs the job): seven weeks from permit issuance, countertop allowance $6,500 installed, tile allowance $1,200 material for about 40 square feet with labor included, flooring allowance $4,200 installed, changes priced at cost plus 15 percent. The owners supply the cabinets (Fenwick Cabinetry, from the kitchen designer Marcus Pell's plan, revision 3), the appliances, the sink and the faucet. The same log, with calendar dates, is the example in the selection and procurement log. Every name and number is invented.

The sequence the contractor planned

WeekWorkWhat has to be on site or decided
1Containment, demolition to studs, dumpsterCabinet layout final (rough-in is set to it)
2Frame the wall opening; plumbing and electrical rough-in to the cabinet layoutSink and faucet installation sheets; dishwasher and range installation guides
3Rough-in inspections; insulation at the exterior wall; drywall hungCountertop material chosen and held at the yard (fabricator's request); tile chosen and ordered
4Drywall taped and primed; flooring installed (chosen before start, acclimated in the living room since week 2); cabinets delivered FridayFlooring on site week 2; cabinets delivered assembled, Friday of week 4
5Cabinets set, leveled, anchored Monday to Wednesday; countertop template ThursdaySink, cooktop and faucet on site Thursday morning
6Fabrication (10 working days); trim, paint first coatTile on site by Friday
7Countertop install Monday; backsplash tile Wednesday to Friday; finish plumbing and electrical; appliance hookup; final inspections FridayEverything

The selection log, as it stood at the end of week 2

Item (mark)Allowance or basisNeeded on siteLead time (quoted)Decide byApprovesVerify before orderStatus, end of week 2
Cabinets, Fenwick Cabinetry, painted shaker (owner-supplied)Owner's purchase, $14,800Fri wk 48 weeks4 weeks before permitOwner, with the designer's layout sign-off (Pell plan rev. 3)Ordered from the designer's measurements with 2-inch fillers at both walls, because the lead time did not allow waiting for demolition; fillers absorb up to 1.5 inches; contractor confirms wall conditions after demo (done wk 1, within tolerance). Range and dishwasher dims from the manufacturers' installation sheetsReleased 4 weeks before permit; dealer confirms delivery Fri wk 4
Range, 30 in. slide-in electric (owner-supplied)Owner's purchase, $2,300Wk 7, but dims needed before cabinet order3 weeks; retailer holds until install weekBefore cabinet orderOwnerCabinet cutout width from the manufacturer's installation sheet, not the brochure; circuit requirement to the electrician before rough-inOrdered; retailer holding
Dishwasher, 24 in. built-in (owner-supplied)Owner's purchase, $1,150Wk 7; spec sheet before rough-in and before cabinets2 weeks; retailer holds until install weekBefore cabinet orderOwnerSpec sheet sent to the electrician and the cabinet installer before rough-in; the unit itself not wanted on site until week 7Ordered; retailer holding
Sink, undermount (P-1, owner-supplied)Owner's purchase, $480Thu wk 5 (template)In stockBefore rough-in (wk 1)Owner; plumber given the sheetBase cabinet width: schedule said 30 in. minimum; sink chosen needs 33; cabinet order corrected to 33 before releaseDelivered wk 2: carton dented, sink dented. Noted on the receipt, photographed; replacement promised wk 4
Faucet (P-2, owner-supplied)Owner's purchase, $420Thu wk 5 (template)In stock in brushed nickel; 6 to 8 weeks in the unlacquered brass they likedWk 1OwnerSingle hole, matches P-1; finish decided (brushed nickel, because of the lead time)On site, checked against the parts list
Countertop$6,500 installed allowanceMon wk 7 (install); template Thu wk 5Fabrication 10 working days after template; slab must be in the yard before templateEnd of wk 3Owner signs selection sheet; contractor issues change order for any overageTemplate only after cabinets set; sink, cooktop, faucet on siteNot decided. Owners want to see the cabinets in first.
Backsplash tile$1,200 material allowance, ~40 sq ft, labor includedFri wk 6Stock: days; the 3 by 9 handmade-look line they like: 3 weeksEnd of wk 3Owner signs; contractor confirms quantity with the setterSetter's layout: plan quantity plus 10 percent overage; quoted $1,340 material, same basis as the allowanceDecided wk 2; ordered; due wk 5
Flooring, engineered oak$4,200 installed allowance; quoted $4,600 installedWk 2 to acclimate; install wk 44 weeksBefore startOwner signed 5 weeks before permitBefore-cabinets decision made (the oak runs under the cabinets); ordered from plan quantity plus 10 percent because the order-by date fell before demolitionOn site, acclimating in the living room
Cabinet hardwareNot in contract; owner-suppliedWk 7In stockWk 5OwnerCount from the shop drawing: 31 pulls, 14 knobsNot decided; low risk
Paint colorIn contract; two coatsWk 6DaysWk 4OwnerSample on the primed wallNot decided; low risk

Notice what the log already caught. The sink needed a wider base cabinet than the schedule's minimum, and because the owners checked the sink against the schedule line before releasing the cabinets, one cabinet width changed on the shop drawing for the price of an email. The cabinets had to be ordered before demolition to make the schedule at all, so the owners and the designer took that risk knowingly, with fillers to absorb what the walls might turn out to be. The faucet finish the owners preferred had a lead time that would have missed template day, so they chose the stock finish, knowingly. The sink arrived dented in week 2, which is exactly why owner-supplied items are asked for weeks before they are needed. All of that is the log working.

The late choice

The countertop was due by the end of week 3. The owners wanted to see the cabinets installed before choosing between two quartz samples, which is an understandable wish and a wrong deadline. They chose on Wednesday of week 5, with the cabinets in. The fabricator templated on Thursday as planned, because templating does not need the slab. But the quartz they chose was not in the yard: two weeks to source. The slab arrived at the start of week 8; fabrication took its ten working days; the countertop was installed on Monday of week 10, three weeks late.

Here is what the three weeks did to everyone else.

ItemPlannedActualWhy
Countertop installMon wk 7Mon wk 10Slab sourced after the late choice
Backsplash tileWed to Fri wk 7Wk 11Tile goes on after the countertop; the setter's next opening after losing the week 7 slot was week 11
Finish plumbing (sink, faucet, dishwasher)Thu wk 7Tue wk 10Nothing to set the sink into until the top is in; plumber's return trip charged at $250
Range and refrigerator set, electrical trim-outFri wk 7Wk 10Appliances sat in the garage, in their cartons, three extra weeks
Final inspectionsFri wk 7Wk 11Nothing to inspect until the plumbing and electrical finish was done
Hale & Daughters crewOn site wk 7Trim and paint in wk 6 and 7, then off site weeks 8 and 9, back wk 10The contractor wrote to the owners in week 5: an owner-caused delay under the contract, the schedule extended three weeks, no charge for the first remobilization
Owners' temporary kitchen7 weeks11 weeksFour more weeks of takeout and the microwave in the dining room

The money. The quartz came to $7,150 installed against the $6,500 allowance: an overage of $650, plus 15 percent markup, a change order of $748, which the owners expected and had budgeted from the contingency (the flooring and tile overages, $460 and $161 with markup, had already been recorded the same way). The plumber's return trip, $250, was passed through at cost. The contractor charged nothing for remobilizing. The real cost was four weeks of a household without a kitchen and three trades rebooked, and none of it appears on an invoice.

What would have changed it: a decide-by date on the log that the owners treated as a hold point. The samples could have been taken to the cabinet showroom in week 2 and held against the door style; the fabricator could have held both slabs for a week while they decided; or, if seeing the cabinets in place was non-negotiable, the owners could have asked the contractor in week 1 what a three-week countertop slip would cost everyone, and planned the sequence around it. Any of those is a decision. Waiting was not.

9. Practice: build your selection log with deadlines Practice

Time: about 60 minutes, plus the calls it generates. Open the selection and procurement log; its example rows are the Alder Street log above, with calendar dates in place of week numbers. Then:

  1. List every selection your project has, one row each, including the ones the proposal called allowances, the ones you plan to supply yourself, and the ones nobody has mentioned (hardware, paint, grout color, light bulbs, the mailbox). Use the finish, door and window, and fixture schedules if you have drawings; use the Module 6 budget categories if you do not. Write the schedule mark on the row where there is one.
  2. Write the needed-on-site date for each row from your sequence (Module 5) or from your contractor's schedule. If you do not have a date yet, write the phase ("before plumbing rough-in") and come back to it from Module 9.
  3. Get lead times in writing. For every row with a lead time you have not been quoted, send an email today asking for the current lead time for the specific product, the release step, and the restocking terms. Enter the answers as they arrive, with the date.
  4. Compute decide-by for each row: needed-on-site minus lead time minus approval and verification time minus a buffer. Sort the log by that column. The top rows are this week's work.
  5. Fill the verification and approval columns: what has to be measured before the order, who approves in writing. For owner-supplied rows, add who receives the delivery and where it will be stored.
  6. Mark the pre-permit rows. Any row whose decide-by date falls before your permit is expected is a section 5 risk. List those separately and take the list to your designer with the question "which of these could plan review change?"

Then compare your log against the criteria in Check your work.

10. Your project Your project

11. Check your work Check your work

Criteria

  • Every selection is a row, including owner-supplied items and the items the proposal did not mention. No allowance in the contract lacks a row.
  • Every row has a needed-on-site date or phase, a lead time with its source and date, and a decide-by date computed from them, not from your calendar.
  • Every row names what must be verified in the field before ordering, and who approves in writing.
  • Rows whose decide-by date falls before the permit are listed separately as accepted risks, with the designer's view recorded.
  • Owner-supplied rows say who receives the delivery, who inspects it, where it is stored, and what happens if it is late, wrong or damaged.
  • Each row carries its schedule mark where the drawings have one, and the schedule line has been read in full.

Worked example: one row, done fully

FieldAlder Street countertop, as it should have been written in week 1
Item and markKitchen countertop, quartz, per finish schedule line K-CT; allowance $6,500 installed
Needed on siteInstall Monday week 7; template Thursday week 5
Lead time (source, date)Fabricator's email, week −1: 10 working days after template; material must be in their yard before template; sourcing 0 days if from stock, up to 2 weeks otherwise
Approval and verificationOwner signs selection sheet; contractor issues change order for the overage before fabrication; template only after cabinets are set; sink, faucet and cooktop on site Thursday week 5
Decide byEnd of week 3 (template Thursday week 5, minus the fabricator's "up to 2 weeks" to source a slab). Assumption: the 2 weeks is the fabricator's figure for their usual yards; a slab from elsewhere could take longer, so the date holds only for what they can source. Later than week 3 is safe only if the fabricator confirms in writing that the chosen slab is already in their yard.
Risk if missedEvery finish item behind the countertop slips: tile, finish plumbing, appliances, final inspection. Ask the contractor in week 1 what the contract does with an owner-caused delay.
StatusTwo samples in hand week 1; taken to the cabinet showroom week 2; decision made week 3 with the fabricator confirming which slab is in stock

Common mistakes

  • Setting decide-by from your own readiness. "After we see the cabinets" is a wish. Build the date backward and, if it is uncomfortable, deal with the discomfort in week one.
  • Ordering to the drawings. Plans say what was intended. Measure what was built, or make sure someone has.
  • Treating a lead time from a web page as a quote. Lead times move by month and by finish. Ask, in writing, for the specific product.
  • Buying owner-supplied items without closing the gap. If nobody has agreed who receives, inspects and stores your purchases, the first damaged carton is a dispute.
  • Signing clean at the delivery door. "Subject to inspection" is not a damage note. Describe the damage, photograph it with the packaging, and know the claims window beforehand.
  • Releasing a custom order before the permit without writing down why. The risk may be worth taking; take it on purpose, with the designer's view and the restocking terms recorded.

What is still unresolved after this module

  • Needed-on-site dates for rows that depend on a look-ahead schedule you have not built yet (Module 9).
  • Which pre-permit items plan review could change: the designer's view, and the building department's if the designer is unsure.
  • How your contract handles a missed selection date: read the clause, or ask your contractor and record the answer.
  • Whether your lender pays for stored materials or deposits, and when.
  • Who, on your project, performs the submittal review for fabricated items, and what each fabricator's release step is.

12. Knowledge check and scenario

The cabinets are set on Monday of week 5, the fabricator needs ten working days after template, and template is Thursday of week 5. When must the countertop material be chosen, and why is that not the same as the template date?
The material has to be chosen early enough for the fabricator to have the slab in the yard before template day, which for a non-stock material can mean two weeks earlier, so roughly the end of week 3. Template measures the cabinets; it does not need the slab in hand, which is why the fabricator can template on time and still be unable to start cutting. The decide-by date is set by sourcing, not by the template.
Name four things that must be on site or true before a countertop can be templated.
Cabinets installed, level and anchored; the sink physically on site; the cooktop or range on site (or its exact installation sheet, if the fabricator accepts that); the faucet on site so hole positions are taken from the real object. Fabricators commonly state that changes after template are not accepted.
What is the difference between "approved" and "approved as noted" on a shop drawing, and why does it matter?
"Approved" means build it as drawn. "Approved as noted" means build it with the corrections written on the drawing, which can change a dimension or a material. It reads as a yes, so people skip the notes. The notes are the point. A note such as "verify all dimensions in field" also moves the measuring responsibility back to whoever ordered.
You arrive home to find the delivery driver has gone and your contractor's carpenter signed for your owner-supplied range. The carton has a crushed corner. What has probably happened to your claim, and what would have prevented it?
A clean signature on the delivery receipt generally accepts the shipment as it is, and the carrier claim may be lost; the visible-damage window in the retailer examples the course found was 24 to 48 hours, so act the same day regardless. Prevention: an agreement before the first order about who receives owner-supplied deliveries, that they inspect before signing, note damage in specific words and photograph it with the packaging; and a delivery time you or that person could actually meet.
Why does the course call ordering before the permit a conversion of a reversible decision into a commitment, rather than simply a bad idea?
Because it is often necessary (windows for dry-in, trusses, custom cabinets) and the risk is specific and manageable. Plan review can change window sizes, glazing, truss profiles or walls; an item already released is then owned and often non-returnable. The middle path is to prepare everything short of release, ask the designer which items review could affect, release early only what is unlikely to change, write down why, and tell the lender. The decision is reasonable when it is made knowingly.
Scenario: the cabinet dealer calls. "If you release the order today we make your week 4 delivery. If you wait for the permit, you are looking at week 7 and your contractor will be sitting idle." Your permit application has been in review for two weeks; the kitchen walls are not changing, but the plan does remove a section of the wall to the dining room, and the engineer's letter is in the package. What do you do?
The reasoning is probably right and the process is wrong. The cabinets along the wall being opened have a run length that depends on where the opening lands, and a reviewer's comment on the header or the opening width could move a cabinet. You may well end up releasing today; the point is to know which cabinets carry the risk before you do, and what a reorder of those would cost.
This is the course's answer. The designer can often say quickly which dimensions plan review could touch (here, probably the run beside the opening, but that is the designer's call, not the course's) and the dealer can tell you whether a single changed cabinet is a reorder or a modification. With both in hand, releasing today is a knowing risk with a known size, which is the only kind worth taking. Record the call and the terms on the selection log row.
Safe, and defensible, but it is not a rule; it is a policy that costs three weeks here and may be the right policy for windows and the wrong one for interior cabinets. The course prefers that you take the question to the designer and decide per item. If the designer says the opening could move the run, waiting is correct for those cabinets and you might still release the rest.

Before you move on