Module 3
Module 3

Understand the team and the language

A building project is a conversation among a dozen people who have never all been in the same room, carried on through drawings, forms and short phone calls, in a vocabulary that nobody taught you. This module introduces the people, the documents that move between them, a plain way to write down who decides what, the thirty terms you will meet most often, and enough about reading a drawing set to find what you need and notice what is missing.

1. Who does what Understand

Not every project has every role, and on a small job one person may hold several. What matters is that every role that exists on your project has a name beside it, and that you know what each one does not do, because the gaps between roles are where problems live.

RoleWhat they doWhat they do not doWhen they enter; who pays them
ArchitectTurns your brief into a design and then into construction drawings; coordinates the engineer; may provide construction administration (periodic site visits, reviewing contractor payment requests, answering questions, certifying substantial completion). Licensed; required for some projects by local rule.Does not build, does not control the contractor's methods, sequence or safety, and does not inspect in the code sense. Under common owner-architect agreements, site visits are "at intervals" to become generally familiar with progress, not exhaustive inspections.Design; sometimes through closeout. Paid by you, by fee or percentage.
Designer (interior, kitchen and bath, or drafting service)Space planning, selections, layouts, sometimes permit drawings for work that does not require an architect's stamp.Does not provide structural judgments; may not be able to sign drawings for permit, depending on the jurisdiction and the work.Design and selections. Paid by you; sometimes through product markup.
Engineer (structural; sometimes civil, geotechnical, mechanical)Designs the structure (beams, footings, connections), the site drainage, the soils report, or the mechanical systems; issues observation letters when asked; answers requests for information about their drawings.Does not inspect for code (that is the building official); does not design what is not in their scope.Design; site visits at key points. Paid by you or through the architect.
General contractor (GC)Prices the work, holds the subcontracts, schedules and supervises the trades, orders most materials, pulls the permit (usually), calls inspections, warrants the work to the extent the contract says.Does not design; is not usually responsible for errors in the drawings, though the contract says where that line sits; does not answer for work carved out of their contract.Bidding through warranty period. Paid by you per the contract.
Construction manager or owner's consultantAdvises you on bidding, scheduling, invoices and quality; may run the site day to day; does not hold the trade contracts (you do).Does not guarantee a price; does not take on the permit responsibility unless the arrangement says so; in California, for example, the licensing board says a consultant cannot manage construction for a fee without a license; ask your state's licensing authority whether the same applies.Any time. Paid by you.
Subcontractors (the trades)Excavation, concrete, framing, roofing, windows, siding, plumbing, electrical, HVAC, insulation, drywall, tile, finish carpentry, paint, flooring. Each prices and performs its own scope and usually pulls its own trade permit where required.Does not coordinate with the other trades unless someone makes them; does not check that scopes fit together.Construction. Paid by the GC, or by you if you hold the contracts.
SuppliersLumberyard, window dealer, cabinet shop, tile showroom, plumbing supply, appliance dealer. Quote, take orders, deliver, sometimes field-measure and produce shop drawings.Do not install (usually); do not verify your dimensions unless they measure.Design (quotes) through finishes. Paid by whoever orders.
Building official and inspectorsReview plans for the adopted codes, issue the permit, inspect at hold points, issue the final approval or certificate of occupancy. Answer questions about what is required.Do not design, supervise, or check quality beyond the code; do not resolve disputes between you and the contractor; passing an inspection is not acceptance of the work.Permit application through final. Fees paid by the permit applicant.
Lender and draw inspectorApproves the budget, disburses funds in draws against work in place, sends an inspector to confirm that billed work is there.The draw inspector checks that work is in place for payment, not that it meets code or the drawings.Before construction through final draw. Fees in the loan.
Insurance agentTells you in writing what your policy covers during construction; quotes builder's-risk and liability coverage; reads contractors' certificates of insurance for you.Does not evaluate the contractor's work.Before contracts are signed. Paid through premiums.
AttorneyReads contracts before you sign; explains lien, deposit and payment rules in your state; drafts or reviews changes to standard forms.Does not manage the project.Before signing. Paid by you, hourly.
SurveyorLocates lot lines and easements; stakes the building; may be required to certify the foundation's location before or after the footing inspection; produces an as-built survey at closeout where required.Does not design the site.Design (boundary), footing stage, closeout. Paid by you.
Testing agenciesHazardous-materials sampling (lead, asbestos); soils and compaction testing; energy testing (blower door, duct leakage); water testing for wells; septic inspection.Do not interpret beyond their report.At specific points; each has its own lead time and may require a retest.
UtilityConfirms service availability (sometimes a "will-serve" letter), schedules service upgrades, new meters and connections, disconnects and reconnects.Works on its own schedule, which may be the longest lead time on the project.Feasibility onward. Fees to you.
YouOwn the goals, the brief, the money, the selections and the decisions; hire and pay; keep the records.See the boundary at the end of section 5.Throughout.
The judgment behind it

One of the most common failures in a residential project is not a bad trade; it is a task that two people each assumed the other owned. Who orders the windows? Who measures the openings? Who calls the utility? Who protects the hall floor? The responsibility map in section 3 exists to make those assumptions visible before they cost anything.

2. How information moves

Each role communicates through a small set of documents. Once you know what each document is for, who writes it and who it binds, most of the vocabulary falls into place.

DocumentWho produces itWho receives itWhat it settles
Drawings (plans, elevations, sections, details, schedules)Architect, designer, engineerBuilding department, bidders, contractor, trades, suppliersWhat is built and where; dimensions; how parts connect
SpecificationsArchitect or designer; sometimes the contractorBidders, contractor, tradesWhat materials and products, to what standard, installed how
Scope narrativeYou (from the brief), or the designerBidders, contractorWhat the drawings do not show: conditions, exclusions, owner-supplied items, expectations in plain words
ProposalContractor or tradeYouA priced offer for a described scope with terms (Module 7)
ContractContractor's form, a standard form, or an attorney's draftBoth parties signEverything: scope, price, payment, schedule, changes, warranty, disputes. Some states require specific contents; Massachusetts, for example, requires home improvement contracts over $1,000 to be written and to include start and substantial-completion dates and a payment schedule. Yours go to an adviser before signing.
Submittals (product data, samples, shop drawings)Contractor or supplierDesigner or you, for review before ordering or fabricatingThat what will be ordered matches what was specified; returned "approved," "approved as noted" or "revise and resubmit." "Approved as noted" can change a dimension while reading as approval.
Request for information (RFI)Contractor or trade (or you)Designer or engineerA written question where the drawings are unclear, conflicting or silent; logged, dated, with the schedule impact stated. Ask well before the answer is needed; one common suggestion is around ten days.
Change orderContractor proposes; you approve (or the reverse)Both signA change to scope, price or time, in writing, before the work (Module 6 and Module 11)
Meeting notesWhoever runs the meeting (often you)Everyone presentDecisions, open items, who does what by when (Module 9)
Daily logContractor's lead; you, if you are coordinatingThe fileWeather, who was on site, deliveries, inspections, problems; the record disputes are settled with
Inspection recordBuilding inspectorPermit holderPassed, failed, or conditional at each hold point
Pay application and lien waiversContractorYou (and the lender)What is billed, against what schedule of values, with releases from subs and suppliers (Module 6)

The practical rule: decisions travel in writing, in one channel; chatter can travel any way it likes. A decision made by phone or text is restated in writing by whoever made it, the same day, and goes in the decision log.

3. The responsibility map

A responsibility map lists the tasks that matter and says, for each, who decides, who does, who is consulted before it happens, and who is informed after. Project managers call this a RACI chart; the plain words are better. One person decides each task. If two people decide, nobody does.

Fictional example

The Dunmores' Fennimore Road primary suite from Module 2, now in design. The team: Marisol Achterberg, architect, providing limited construction administration (site visits at four milestones and answering RFIs); a structural engineer she retains; Stillwater Builders, a general contractor on a fixed-price contract, with its own plumbing, electrical and HVAC subcontractors; the town building department; no lender draws (savings and a home-equity line). The Dunmores are informed homeowners. All names are invented.

TaskDecidesDoesConsultedInformed
Side setback and whether the footprint fitsBuilding department (the rule); Dunmores (the footprint)Architect (asks, draws)SurveyorStillwater
Beam over the new doorway to the hallEngineerEngineer (designs); Stillwater (builds)ArchitectDunmores, building department (via drawings)
Panel capacity and any service upgradeDunmores (whether to upgrade, on the electrician's assessment)Stillwater's electrician (assesses, installs); Stillwater (calls the utility); utility (service)ArchitectBuilding department
Hazardous-materials sampling of the porch ceilingDunmoresTesting firmStillwater (what gets disturbed)Architect
Tile selection and allowanceDunmores, by the date tied to the plumbing rough-inDunmores (select); Stillwater (orders, installs)Architect (layout), tile supplier (lead time)Plumber (drain position)
Window order and rough openingsArchitect (sizes, per the drawings); Stillwater (release to order)Stillwater (field-measures, orders)Window dealerDunmores
Calling inspectionsStillwaterStillwaterSubs (readiness)Dunmores
Approving a change orderDunmoresStillwater (prices, performs)Architect (is it a real change?)Affected subs
Protection of the dining room and hall during demolitionStillwater (method)StillwaterDunmores (what matters to them)-
Keeping the dog out of the work zoneDunmoresDunmoresStillwater (where the barrier is)Subs
Substantial completionArchitect certifies; Dunmores acceptStillwater (punch list)Building department (final inspection is separate)-

Two things to notice. First, the Dunmores decide more than they expected, and most of their decisions have dates. Second, the map found a gap on the first pass: nobody had been assigned to call the utility about the service upgrade. In the version above the call belongs to Stillwater, because someone asked; section 9 shows that row before and after.

4. Essential terminology

These are the thirty terms used most often in Modules 4 through 11. Each is explained again the first time a module uses it, so you do not need to memorize them now; read the list once so the words are familiar. The full glossary has the rest.

TermMeaningWhere you will meet it
AllowanceA placeholder sum in a price for something not yet selected; ask whether it covers material only or installed, with or without tax, delivery and markupModules 6, 7, 8
AlternateA separately priced option (add or deduct) so a decision can be made with a number in handModules 2, 7
As-built (record) drawingsDrawings marked to show what was actually built, including concealed runsModules 10, 11
Bid, quote, proposalA priced offer for a described scope; a proposal adds the contractor's termsModule 7
Certificate of insurance (COI)A document from an insurer or broker showing what coverage existed on the date issued; not a policy, and not coverage for youModules 4, 7
Certificate of occupancy (CO), final approvalThe building authority's approval to occupy or use; separate from the contract's completionModules 5, 11
Change order (CO)A signed change to scope, price or time; priced and signed before the workModules 6, 9, 11
ContingencyMoney held for the unknown; the owner's contingency is outside the contract and is not for upgradesModule 6
Cost-plus, lump sum, time and materials (T&M)Price structures: actual cost plus a fee; one fixed price; hourly plus materialsModules 1, 7
DrawA disbursement from a construction loan, usually after an inspector confirms work in placeModules 4, 6
Dry-in (weather-tight)The point at which roof, sheathing, water-resistive barrier, windows and doors keep weather outModule 5
ElevationA drawing of a vertical face (exterior or interior wall) as seen straight onModule 3, 8
ExclusionSomething a reader might assume is included and is not; written as a listModules 2, 7
Finish scheduleA table listing, room by room, the floor, wall, ceiling and trim finishesModules 3, 8
Hold point, inspectionA stage where work must stop until an inspector approves it; covering work before inspection can force removalModule 5
Lead timeTime from order to delivery; the course asks for a written quote for every long-lead itemModules 5, 8
Lien, lien waiverA claim against the property by an unpaid contractor, sub or supplier; a waiver releases it, conditional on payment or unconditionalModules 4, 6, 11
Look-ahead scheduleA two- or three-week list of what happens next, with crews, materials and prerequisites namedModule 9
Means and methodsHow a contractor performs the work; the contractor's responsibility, which an owner who starts directing can take onModules 3, 9, 10
Permit, plan review (plan check)The authority's permission to build, issued after its review of the drawings; correction cycles can restart the clockModules 4, 5
Punch listThe numbered list of incomplete or defective items at the end, with responsible party and due dateModule 11
RetainageA percentage held from each payment until completion; leverage for the punch listModules 6, 7, 11
Request for information (RFI)A logged written question to the designer or engineer where the drawings are unclear or silentModules 3, 9, 10
Rough-in, trim-out (finish)The concealed stage of plumbing, electrical and HVAC, done with walls open; then the visible stage after finishesModules 5, 8
Schedule of values (SOV)The contract price broken into line items, each billed by percent completeModules 6, 7
ScopeThe described work: where, what, how much, to what standard, who suppliesEverywhere
Section, detailA drawing cut through the building to show construction; an enlarged drawing of one junctionModule 3, 10
Specification (spec)Written requirements for materials, products and workmanship, organized by trade or sectionModules 3, 7, 8
Submittal, shop drawingThe package a contractor or supplier sends for review before ordering or fabricating; a shop drawing shows how a fabricated item will be builtModule 8
Substantial completionThe contract milestone at which the work can be used for its purpose with minor items remaining; the date many warranties and responsibilities startModule 11

5. Reading a drawing set

A set of construction drawings is a stack of numbered sheets, each a different view of the same building. The sheets reference each other with symbols. Once you can follow the references, you can find anything in the set, and more usefully, you can notice what is not there.

What the sheets are

  • Sheet index (usually on the cover or the first sheet): the list of every sheet in the set with its number and title. Read it first. It is the table of contents and the quickest way to see whether, for example, there is no electrical plan.
  • Site plan: the lot, the building footprint, setbacks, utilities, drainage, trees, where the dumpster and deliveries go. Often required for additions and new buildings.
  • Plans: horizontal cuts through the building about four feet above the floor, one per level, looking down. Walls, doors, windows, fixtures, cabinets, dimensions. A demolition plan shows what is removed; a reflected ceiling plan shows lights and ceiling features as if seen in a mirror on the floor.
  • Elevations: each exterior face seen straight on (heights, roof lines, windows, materials); interior elevations for kitchens, bathrooms and built-ins (cabinet heights, tile extents, fixture positions).
  • Sections: vertical cuts through the building, showing foundation, floor, wall and roof construction and heights. The cut line is marked on the plan with a symbol that tells you which sheet the section is on.
  • Details: enlarged drawings of junctions (a window sill, the roof-to-wall flashing, a footing). Referenced from plans, sections and elevations by a circle with the detail number and the sheet number.
  • Schedules: tables. A door schedule lists every door by tag number with size, type, material, hardware and fire rating. A window schedule does the same for windows, with sizes, operation, glazing and energy values. A finish schedule lists, for each room, the floor, base, walls, ceiling and any notes. A fixture schedule or lighting schedule lists products. Schedules are where "to what standard" lives.
  • Structural sheets (often prefixed S): foundation plan, framing plans, beam and header sizes, connection details, the engineer's general notes.
  • Mechanical, electrical, plumbing sheets (M, E, P), where they exist: on many small residential sets they do not, and the trades lay out their own work from the plans and the code. That is a thing to know, not a defect.
  • General notes: paragraphs of text, usually on the cover or first sheet, that apply everywhere. They often contain the most consequential sentences in the set ("contractor to verify all dimensions in field," "all work to comply with the adopted codes," "existing conditions shown are approximate").

Scale

Drawings are drawn to scale: a stated ratio between the drawing and the building. Residential plans in the United States are commonly drawn at 1/4 inch to the foot (a quarter inch on paper is one foot in the building); details are drawn larger, at 1 inch or 1 1/2 inches to the foot. The scale is written under each drawing's title. Two warnings. First, never scale a printed drawing with a ruler to get a dimension that is not written; prints come out at odd sizes, and by convention the written dimension governs; many sets say so in the general notes. Second, "NTS" means not to scale.

How the symbols connect the sheets

  • A door tag (a number in a circle or hexagon beside a door) points to the door schedule.
  • A window tag (a letter or number in a different shape) points to the window schedule.
  • A section marker (a line across the plan with a circle at each end, an arrow for the viewing direction, and a number over a sheet number) says "section 2 on sheet A-3 is cut here, looking that way."
  • A detail callout (a circle around part of a drawing with a number over a sheet number) says "this junction is drawn larger as detail 5 on sheet A-5."
  • A room name and number on the plan points to the finish schedule.
  • A revision cloud (a scalloped outline) with a triangle and a number marks what changed in a revision; the revision block in the title block lists the dates.

Finding what is not drawn

This is the owner's most useful drawing-reading skill, because what is not drawn is unconfirmed: it may not be priced, and it may not be built the way you imagine. Four habits:

  1. Compare the sheet index with the brief. If the brief has a bathroom and there is no interior elevation of it, tile heights and niche positions are undecided. If there is no electrical plan, nobody has drawn where the lights go.
  2. Read every note and look for the hedges: "by others," "NIC" (not in contract), "existing to remain," "verify in field," "to be selected," "see spec." Each one is a boundary of the drawings' responsibility, and each one needs an owner: a person, an allowance, or a date.
  3. Follow one element all the way through. Take a window: find its tag on the plan, its size on the schedule, its head and sill in a section, its flashing in a detail, its exterior trim on an elevation. If any step is missing, that is a question.
  4. Look for the transitions: where new meets existing, floor meets floor, roof meets wall, inside meets outside. Transitions are among the hardest things to draw and the most commonly left out.
Boundary

Reading drawings is not the same as checking them. You are reading in order to understand, to find the right sheet, to ask good questions and to notice what is missing. Whether a beam is sized correctly, whether a detail will keep water out, whether the set meets the code: those are the design professional's responsibility and the building official's job, respectively, and nothing in this course qualifies you to take either on. When something looks wrong to you, the response is a written question to the person whose job it is, not a field decision and not silence.

6. See it: a plan sheet, annotated; a specification beside a scope narrative See it

A simplified floor plan sheet with its parts labelled A rectangular drawing sheet. Along the right edge is a title block with the project name, sheet number A-2, scale and revision list. The main area shows a simple plan of a bedroom, closet and bathroom with wall lines, a door tag numbered 1 in a circle, a window tag labelled B in a hexagon, a dimension string along the bottom, a section marker labelled 1 over A-3 cutting through the bathroom, a detail callout labelled 5 over A-5 at a corner, a north arrow at top left, a general notes column at the lower left, and a revision cloud around the bathroom door. Callout labels around the drawing name each part. FENNIMORE ROADPRIMARY SUITEM. Achterberg, Architect(fictional) REVISIONS 1 setback 2 Apr2 bath door 9 May SCALE1/4" = 1'-0" DATE 9 May SHEETA-2 of 9 N PRIMARY BEDROOM101 CLOSET102 BATH103 1 2 B 15'-0"9'-0" 1A-31A-3 5A-5 2 GENERAL NOTES 1. Verify all dimensions in field. 2. Existing conditions approximate. 3. Tile extents: see int. elevs A-4. 4. Vanity by owner, NIC. title block: sheet number,scale, revisions, date door tag 1: see door schedule window tag B: see window schedule section 1/A-3: cut here,drawn on sheet A-3 detail 5/A-5: this corner,enlarged on sheet A-5 revision cloud 2:bath door changed 9 May dimension string: writtendimensions govern
A simplified plan sheet, A-2 of 9, for the fictional Fennimore Road suite. Follow one element to see how the sheets connect: door 1 on the plan is sized on the door schedule; section 1 through the bathroom is drawn on A-3; the corner where new meets existing is enlarged as detail 5 on A-5; general note 4 says the vanity is not in the contract; note 3 sends tile extents to the interior elevations on A-4. If sheet A-4 were missing from the index, the tile would be undecided.

A specification beside a scope narrative

A specification is written by a designer for a contractor. It is organized by product or trade and says exactly what material, what product or standard, and how it is to be installed. A scope narrative is written by you (or with your designer) for bidders. It is organized by room and says what the drawings do not: conditions, expectations, exclusions, who supplies what. The same bathroom, in both:

SPECIFICATION (excerpt) SECTION 09 30 00: TILING Floor tile: porcelain, 12 x 24 in., slip resistance suitable for wet areas, owner-selected within allowance of $14/sq ft material.A product requirement with a standard and an allowance. Addressed to the installer. Setting: thin-set per manufacturer; membrane under shower floor per manufacturer's system; movement joints at perimeter and changes of plane. Grout: cementitious, color by owner; sealed. Extent: floor throughout; walls full height in shower; see A-4.Extent lives in the drawings; the spec points there. Submittals: product data and one sample tile for approval before order.
SCOPE NARRATIVE (excerpt) PRIMARY BATHROOM (new, approx. 9 x 11 ft) We will choose the tile; carry $14/sq ft material in your price and tell us what "installed" would add per square foot if we go over.Same allowance, in plain words, with a question built in. Shower is curbless with a linear drain; the floor slope matters to us more than anything else in this room. Vanity is ours (60 in.); you install it. Toilet is wall-hung; we have not chosen it; carry $900 installed.Who supplies what; a second allowance with its definition. The hall and the dining room stay in use throughout; protect the hall floor and the dining room windows, and keep the dog out.Conditions and the outside of the work zone, which no spec would say. Not included: closet systems beyond rod and shelf, window coverings, mirrors.

You will rarely write a specification; your designer or contractor will. You will almost always write the scope narrative, and Module 7 shows what happens to bids when nobody does.

7. Practice: map your team and read one sheet Practice

Time: about 45 minutes for the map; 30 minutes for the sheet.

Part 1: the responsibility map

Open the team directory and responsibility map. First, the directory: one row per role on your project, with a name if you have one and "not yet identified" if you do not. Include the roles you have not thought about: insurance agent, attorney, surveyor, testing firm, utility. Then the map:

  1. List twelve to twenty tasks that matter, drawn from your brief's unknowns register and from the Dunmores' example: each authority question, each long-lead order, each selection, calling inspections, protection, change orders, who calls the utility, who measures what.
  2. For each task, write one name in "decides." One. If you want to write two, split the task until each half has one.
  3. Fill "does," "consulted" and "informed." Leave a cell blank rather than guess; a blank is a finding.
  4. Read down the "decides" column. Every task you decide needs a date (Module 8 will assign them). Every task a role you have not hired decides is a reason to hire them before that task comes due.
  5. Read for gaps. Any task with nobody in "does" is the Dunmores' utility call: unowned until someone asks. Assign it or add it to the questions for your next conversation with the contractor or designer.

Part 2: read one sheet

If you have drawings, take one sheet, ideally a plan. If you do not, use the annotated sheet in section 6. For that sheet, write down: the sheet number and what the index says it is; the scale; every symbol that points to another sheet and where it points; every note that hedges ("verify in field," "by others," "NIC," "to be selected"); one element you followed to a schedule, a section or a detail, and whether any step was missing; and two questions the sheet raised that you will write down for the designer. Put the questions in the decision and issue log or, if they are about rules, in the verification list.

8. Your project Your project

9. Check your work Check your work

Criteria

  • The directory has a row for every role in section 1, with a name or "not yet identified"; none is missing because you assumed you would not need it.
  • Every task has exactly one name in "decides."
  • Every blank cell has been noticed and either filled, assigned as a question, or deliberately left as "not applicable."
  • Tasks you decide are flagged as needing dates.
  • The sheet exercise produced at least two written questions, and none of them is phrased as a judgment ("the beam is too small") rather than a question ("is the beam on S-2 sized for the span shown on A-2?").

Worked example

One row of the Dunmores' map, before and after the first review:

Task: electrical service upgrade, if the panel assessment says it is needed BEFORE: Decides: Dunmores. Does: (blank). Consulted: electrician. Informed: Stillwater.The blank is the finding: the assessment was assigned, the upgrade was not, and the utility was nowhere. AFTER: Decides: Dunmores, on the electrician's written assessment, by the date bids go out. Does: Stillwater's electrician (panel work); utility (service and meter); Stillwater (calls the utility and reports the lead time to the Dunmores within a week of the assessment). Consulted: architect (location of the new meter, if any). Informed: building department (via the electrical permit).Three "does" entries, each a different party, and the utility call has an owner and a deadline.

Common mistakes

  • Two deciders. "Architect and owner decide the window sizes" often means the windows get ordered late. Split it: the architect decides sizes per the drawings; the owner decides whether to approve the cost of a change.
  • Mapping only the trades. The utility, the testing firm, the surveyor and the insurance agent have tasks with lead times. Leaving them off the map is one way a service upgrade becomes a long stall.
  • Writing judgments instead of questions. An owner who tells the framer the beam is undersized has stepped across the boundary in section 5. The same concern as a written RFI to the engineer is exactly right.
  • Treating "approved as noted" as approved. Read the notes; they can change a dimension.
  • Assuming a small set has everything. Many residential sets have no electrical or plumbing plan. That is normal; it means the layout decisions happen in the field, and the map should say who makes them and when.

What is still unresolved

  • The names in the "not yet identified" rows, and when each must be hired (Modules 4 and 7).
  • The dates for every task you decide (Module 8).
  • The questions your sheet reading raised, which go to the designer and come back as answers, revisions or RFIs.
  • Whether your jurisdiction requires an architect's or engineer's stamp for your project, which decides whether some rows exist at all (Module 4).

10. Knowledge check and scenario

What does a building inspector's "pass" at the framing inspection tell you, and what does it not?
That, in the inspector's judgment, the items checked at that hold point met the adopted code on that day. It does not say the work matches your drawings beyond what the code requires, that the workmanship is good, or that you have accepted the work. Acceptance is a contract act by you; quality is what your contract and your designer's observation are for.
Who decides, who does, who is consulted and who is informed when a window order is released? Why does it matter that one person decides?
In the Dunmores' example: the architect decides sizes per the drawings and the contractor decides when to release the order; the contractor field-measures and orders; the window dealer is consulted on lead time; the owner is informed. If "decides" has two names, each waits for the other, and the window arrives after the framer needed it.
A drawing says "verify in field" beside a dimension, and another sheet says "vanity NIC." What does each hedge mean for you?
"Verify in field" means the drawing's dimension is not to be trusted until someone measures the actual condition; the map should say who measures and when. "NIC" means not in contract: the vanity is not in the contractor's price, so either you supply it (and the map says who installs it) or it is an unpriced item.
What is the difference between a specification and a scope narrative, and which one will you write?
A specification is written by a designer for a contractor, organized by product or trade, stating materials, standards and installation. A scope narrative is written by you for bidders, organized by room, stating conditions, expectations, exclusions and who supplies what. You will almost always write the narrative; the specification, where one exists, comes from the designer or contractor.
Why does the course say reading drawings is not checking them?
Reading is understanding: finding the sheet, following a symbol, noticing what is missing, asking a question. Checking is judging whether the design is correct and compliant, which is the design professional's responsibility and the building official's job. An owner who starts checking, and directing, takes on responsibility for the result without the training or the authority, and crosses the means-and-methods line that helps keep responsibility with the contractor.
Scenario: you are on site. The framer, who has been doing this for twenty years, points at the beam over the new hall doorway and says, "That looks light to me for that span. I'd go one size up. Want me to?" The engineer's drawing S-2 shows the size he is questioning. What do you do?
You have just made a structural decision, and so has the framer, and neither of you is the engineer. "Bigger" is not always safer: a deeper beam can change the header height, the door, the bearing at each end and the load path below, and a change that is not on the drawings is a change the inspector may ask about and the engineer did not approve. The cost difference is not the point; the responsibility is. This is the boundary in section 5, crossed in one friendly sentence.
This is the course's answer. The framer's experience is valuable and you treated it that way: you wrote his observation down and sent it to the one person whose job it is to answer. The RFI is a question, not a judgment; it names the sheets; it is logged with a date so the delay is visible; and the hold on that element means nothing is built on an answer nobody has given. The engineer may confirm the size in an hour, or may be grateful for the catch. Either way the decision stays where it belongs.
The beam does get built as drawn, which is the right default, and you kept the decision with the engineer. But you threw away a free observation from an experienced person and told him not to offer the next one. A written question costs ten minutes and keeps the framer talking to you, which you will want in month four. Option B gets the same beam, if that is the answer, and better information.

Before you move on